Decision Notice 109/2024
Lochaber Smelter: interactions with Greensill Capital (UK) Limited
Authority: Scottish Ministers
Case Ref: 202200181
Summary
The Applicant asked the Authority for a copy of all interactions with Greensill Capital (UK) Limited in connection with the Lochaber Smelter Guarantee and Reimbursement Agreement (GRA). The Authority disclosed some information, and withheld the remainder under a number of exemptions in FOISA. The Commissioner investigated and found that the Authority had generally complied with FOISA in responding to the request.
Relevant statutory provisions
Freedom of Information (Scotland) Act 2002 (FOISA) sections 1(1), (2), (4) and (6) (General entitlement); 2(1)(b) (Effect of exemptions); 30(c) (Prejudice to effective conduct of public affairs); 47(1) and (2) (Application for decision by Commissioner)
The full text of each of the statutory provisions cited above is reproduced in Appendix 1 to this decision. The Appendix forms part of this decision.
Background
1. On 23 May 2021, the Applicant made a request for information to the Authority. The Applicant asked for a copy of all interactions (to include, but not be limited to, all letters, emails, minutes and notes of meetings) with Greensill Capital (UK) Limited in connection with the Lochaber Smelter GRA.
2. The Authority responded on 22 June 2021, informing the Applicant, in terms of section 17(1) of FOISA, that it did not hold the information requested.
3. On the same day, the Applicant wrote to the Authority requesting a review of its decision. The Applicant stated that they were dissatisfied with the decision because they considered the Authority did hold the information requested.
4. The Authority notified the Applicant of the outcome of its review on 20 July 2021, upholding its original decision without modification.
5. On 3 August 2021, the Applicant wrote to the Commissioner, applying for a decision in terms of section 47(1) of FOISA. This resulted in the Commissioner issuing Decision 046/2022 , requiring the Authority to issue a revised review outcome, otherwise than in terms of section 17(1) of FOISA.
6. On 9 February 2022, the Authority issued its revised review response to the Applicant. The Authority disclosed information in redacted form, withholding the redacted information under the exemptions in sections 33(1)(b) and 38(1)(b) of FOISA.
7. On 9 February 2022, the Applicant wrote to the Commissioner, applying for a decision in terms of section 47(1) of FOISA. The Applicant stated that they were dissatisfied with the outcome of the Authority’s review for the following reasons:
• they considered the Authority held more information than it had provided
• the FOISA exemptions claimed do not apply to the withheld information
• the public interest test was not carried out properly, as it favours disclosure of the withheld information
• they considered there had been a deliberate attempt to conceal the information requested because of the high-profile issues that have been impacting Greensill.
Investigation
8. The Commissioner determined that the application complied with section 47(2) of FOISA and that he had the power to carry out an investigation.
9. The Authority was notified in writing that the Applicant had made a valid application. The Authority was asked to send the Commissioner the information withheld from the Applicant. The Authority provided the information and the case was subsequently allocated to an investigating officer.
10. Section 49(3)(a) of FOISA requires the Commissioner to give public authorities an opportunity to provide comments on an application. The Authority was invited to comment on this application and to answer specific questions. These related to the Authority’s justification for withholding the information requested under the exemptions in sections 33(1)(b) and 38(1)(b) of FOISA.
11. During the investigation, the Authority informed the Commissioner that it wished to withdraw its reliance on the exemption in section 33(1)(b) of FOISA, and instead wished to rely on section 30(c) to withhold the information (for which it provided supporting submissions).
12. On 21 December 2022, the Authority notified the Applicant of its change of position and disclosed to them the name of a senior official it had previously withheld.
13. On 16 February 2023, the Authority provided an updated response to the Applicant. The Authority provided a weblink to information that it had originally not marked for disclosure, but which it subsequently identified had been published in relation to a previous information request . The Authority also disclosed further information from an email dated 31 January 2020, which it had previously withheld.
14. The Authority also provided to the Commissioner an updated copy of an email dated 9 March 2020, as it had located a later version with additional information. During the investigation, the Authority disclosed that email to the Applicant, but withheld some of the additional information under the exemption in section 30(c) of FOISA.
15. During the investigation, the Applicant provided comments on why they considered the public interest test favoured disclosure of the information that was now being withheld under the exemption in section 30(c) of FOISA.
16. The Applicant also confirmed that they did not require the Commissioner to reach a finding on the Authority’s application of the exemption in section 38(1)(b) of FOISA in relation to junior officials.
17. The Commissioner is satisfied that only personal data of junior officials have been withheld under the exemption in section 38(1)(b) of FOISA. Consequently, his investigation has not considered this matter further.
Commissioner’s analysis and findings
18. The Commissioner has considered all of the submissions made to him by the Applicant and the Authority.
Background: Lochaber Smelter Guarantee
19. The Authority provided detailed background information, the following parts of which may be helpful in explaining the background of the Lochaber Smelter Guarantee:
20. The Lochaber aluminium complex in Fort William is the UK’s last remaining aluminium smelter, the operation of which is a key component of Scotland’s industrial capability and a major source of employment in the West Highlands.
21. When Rio Tinto decided to review its Lochaber operations in 2016, the smelter faced the prospect of closure, endangering over 300 jobs in total (direct, indirect and induced). The Authority’s focus at the time was to avoid the fragmentation of the Lochaber complex, to secure the long-term viability of the smelter and to realise further industrial and employment opportunities on site.
22. In September 2016, as part of the Authority’s wider overall objective to preserve jobs, protect the economy and sustain the metals industry in Scotland, it indicated a willingness to support any purchaser who would retain the smelter and associated hydro-power scheme together, and make the necessary commitment to significant investment in the development of the Lochaber assets. The Authority’s offer included the potential to guarantee the power purchase obligations of the aluminium smelter and was made known on an even-handed basis to all short-listed bidders via the vendor (Rio Tinto).
23. To deliver its objective for the site, the Authority is standing behind a portion of the power purchase obligations of the aluminium smelter operator (Alvance British Aluminium Limited (SmelterCo)) in the event that it cannot pay for the power it is contracted to take from the hydro-electric power station operator (Simec Lochaber Hydropower 2 Limited (HydroCo)). Both companies are part of the GFG Alliance (GFG) which is a collection of global businesses and investments.
24. The commercial guarantee arrangement (the Guarantee) was entered into in December 2016 by the Authority, SmelterCo and HydroCo, and guarantees over a 25 year term that the Authority will pay for a percentage of the power that SmelterCo is contracted to purchase from HydroCo in the event that SmelterCo is unable to do so.
25. The nominal value of the Authority’s contingent liability on day one of the Guarantee was £586 million (i.e. the total amount of payments guaranteed by the Authority across the 25 year agreement), and is the largest industrial guarantee ever agreed by the Authority.
26. In return for the Guarantee, the Authority receives a commercial guarantee fee (the Fee) from GFG.
27. In March 2021, GFG’s major providers of working capital and investment finance (Greensill Capital (UK) Limited and Greensill Capital Management Company (UK) Limited (together “Greensill”)) entered administration.
28. The Authority submitted that should the Lochaber Guarantee be called in and if other recovery options prove ineffective, it would have an option to take ownership of the business assets at Lochaber and trade these assets (directly or through lease arrangements) with the intent of satisfying the ongoing payment obligations under the Power Purchase Agreement (PPA) or alternatively seek to dispose of the assets through a managed sales process.
29. The Authority submitted that information within the material remained current and could negatively impact its ability to operate the assets on effective commercial terms and, potentially, inhibit any sale process to the detriment of the public purse if the information was disclosed prematurely.
The Applicant’s perspective
30. Following the issue of Decision 062/23 and Decision 063/23 on 20 June 2023 (which also related to the Lochaber Smelter GRA), the Applicant wrote to the Commissioner (on 21 June 2023 and on 31 July 2023) to advise him that they strongly disagreed with the outcome.
31. The Applicant explained that the Commissioner appeared to have accepted information provided to him by the Authority at face value and without adequate challenge. In their view, the Guarantee did nothing for the preservation of jobs at the smelter, but guaranteed the income for the hydro-plant only, which had very few direct jobs. In their view, “the story of saving jobs is concocted to divert attention away from the real purpose (a financial enabler to allow the GFG Alliance to purchase the company)”.
32. The Applicant also wrote to the Commissioner on 26 June 2023, contesting in more detail the accuracy of the background information provided by the Authority in paragraphs 16 and 13 of those Decisions respectively. The Applicant provided what they described as an “alternative background”, as set out below:
• The primary purpose of the Guarantee was to enable GFG to purchase Alcan Aluminium UK Ltd (Alcan) by issuing debt. The Guarantee did not directly support existing jobs. As part of the agreement, Greensill Capital securitised the guarantee together with forecasted revenue streams from the smelter to the supporting hydro-electric facility in order to provide loan-financing to GFG. In the event that the guarantee was called in, it provided protection to Greensill (now in administration), not companies within GFG.
• While the Authority may claim that the Guarantee was offered on an even-handed basis to all prospective bidders, it strongly favoured bidders using supply-chain finance as the mechanism of acquisition (such as GFG). The offer provided much less advantage, for example, to cash bidders and so the “even-handed” offer merely created an illusion of fairness. The net effect of the guarantee offer to all bidders was to significantly elevate the attractiveness of the debt-financed GFG bid. (The Authority had an already-established relationship with GFG through its purchase of the Dalzell and Clydebridge steelworks.)
• Alcan was not a distressed company at the time of acquisition by GFG and was trading profitably. GFG purchased the company for £330 million. This was not the value of a distressed company. The funding enabled by the Guarantee was not “last resort funding” in relation to the Lochaber complex.
• A stated objective of the Authority was to prevent the fragmentation of the Lochaber smelter complex. However, immediately after the acquisition, GFG removed the Lochaber smelter, Kinlochleven hydro-plant and estate land holdings from the existing legal entity (Alcan), transferring them to new and separate legal entities under different structures ultimately controlled from different off-shore jurisdictions.
• The Authority had represented that, in return for entering into the Guarantee, it received a “commercial fee”. There was no independent evidence to support the assertion that the fee was at a commercial level. If the arrangement was of a commercial level, GFG could have obtained the Guarantee from the private sector where there are much lower transparency expectations.
• High levels of secrecy over high-value government contracts were a red flag of potential fraud. Fraudsters were extremely unlikely to consent to disclosure of any information in any circumstance. GFG is under investigation by the Serious Fraud Office for suspected fraud, fraudulent trading and money-laundering including its financing arrangements with Greensill. The Serious Fraud Office has no jurisdiction in Scotland where there is no equivalent agency.
The Authority’s interests
33. In addition to the background information above, the Authority explained that, as a result of its legal obligations arising from the Guarantee, it had a significant and specific financial and economic interest in the operation of the smelter to which the information related. In addition, it had an overarching general interest in the original objectives of the proposal, namely the retention of jobs and the support of the metals industry in Scotland.
34. The Authority acknowledged that the Commissioner had previously indicated in Decision 144/2021 that he did not consider the Authority to be a commercial actor in respect of Scotland’s energy sector, but that it may have other economic interests in relation to the smelter.
35. The Authority considered that its commercial, economic and financial interests in respect of the Guarantee were manifest and quantifiable, and information within the material remained current. It also submitted that there was considerable uncertainty with respect to any future scenario involving the smelter, the loss of which could materially impact upon the local regional economy. It noted that, during the 18 months since the Greensill collapse, GFG and its primary shareholder, Sanjeev Gupta, had sought to defend and engage in legal action across multiple jurisdictions in order to preserve operations.
Information falling within scope of the request
36. Section 1(1) of FOISA provides that a person who requests information from a Scottish public authority which holds it is entitled to be given that information by the authority, subject to qualifications which, by virtue of section 1(6) of FOISA, allow Scottish public authorities to withhold information or charge a fee for it. The qualifications contained in section 1(6) are not applicable in this case.
37. The information to be given is that held by the authority at the time the request is received, as defined in section 1(4).
38. The standard of proof to determine whether a Scottish public authority holds information is the civil standard of the balance of probabilities. In determining where the balance of probabilities lies, the Commissioner considers the scope, quality, thoroughness and results of the searches carried out by the public authority.
39. The Commissioner also considers, where appropriate, any reason offered by the public authority to explain why it does not hold the information. While it may be relevant as part of this exercise to explore expectations about what the authority should hold, ultimately the Commissioner’s role is to determine what relevant recorded information is (or was, at the time the request was received) actually held by the authority.
40. The Authority identified and provided copies of two documents in redacted form considered to fall within the scope of the request, consisting of seven and eight pages of email correspondence, respectively, dating between 31 January 2020 and 18 May 2020.
41. During the investigation, the Commissioner asked the Authority how it had established what information it held falling within the scope of the request, particularly because one email identified as falling within scope referred to further correspondence which had not been provided.
42. The Authority conducted further searches and, as rehearsed in paragraph 13, disclosed information that had been published online in response to another request, which fell within scope of the Applicant’s request and further information in an email dated 31 January 2020.
43. The Authority also provided, as rehearsed in paragraph 14, an updated version of an email dated 9 March 2020. The Authority withheld some of the additional information within the email under the exemption in section 30(c) of FOISA, together with the information that was previously withheld.
44. Using the following keywords, the Authority carried out searches of its Electronic Record and Document and Management System (eRDM), MiCase system and the mailbox for the relevant business area:
• “Greensill Capital”
• “Greensill”
• “Greensill Capital Guarantee & Reimbursement Agreement”
• “Due diligence on Greensill Capital”
45. In addition to this, the Authority carried out searches of the Strategic Industrial Projects team mailboxes for emails from “@greensillcapital.co.uk”, “@greensillcapital.com” and “Lex Greensill”, as well as for the keywords “Due diligence on Greensill Capital”.
46. The Authority also instructed its legal and commercial advisers to carry out searches (on the same basis as those it carried out on its own systems) for any relevant information held by them on its behalf.
47. The Authority confirmed that it did not hold either the pricing supplements referred to in an email dated 9 March 2020 or the attachment in an email dated 18 April 2020, which were previously held on its behalf by its legal advisers but had not been retained.
48. Following these searches, the Authority confirmed that it held no further information falling within the scope of the Applicant’s request.
The Commissioner’s view
49. Having considered all relevant submissions and the terms the request, the Commissioner is satisfied that, by the end of the investigation, the Authority had taken adequate, proportionate steps in the circumstances to establish whether it held any information that fell within the scope of the request
50. The Commissioner is satisfied that the searches carried out by the Authority were reasonable and sufficient to determine whether the requested information was held. The Commissioner is therefore satisfied, on the balance of probabilities, that the Authority does not (and did not, on receipt of the request) hold any information falling within the scope of the Applicant’s request
51. However, as the Authority disclosed further information to the Applicant subsequent to its review response, the Commissioner must find that the Authority failed to comply with section 1(1) of FOISA.
Section 30(c) – Prejudice to effective conduct of public affairs
52. Section 30(c) of FOISA exempts information if its disclosure "would otherwise prejudice substantially, or be likely to prejudice substantially, the effective conduct of public affairs". This exemption is subject to the public interest test in section 2(1)(b) of FOISA.
53. The word "otherwise" distinguishes the harm required from that envisaged by the exemptions in sections 30(a) and (b). This is a broad exemption and the Commissioner expects any public authority citing it to show what specific harm would (or would be likely to) be caused to the conduct of public affairs by disclosure of the information, and how that harm would be expected to follow from disclosure.
54. The standard to be met in applying the tests contained in section 30(c) is high: the prejudice in question must be substantial and therefore of real and demonstrable significance. The Commissioner expects authorities to demonstrate a real risk or likelihood of substantial prejudice at some time in the near (certainly foreseeable) future, not simply that such prejudice is a remote or hypothetical possibility. Each request should be considered on a case by case basis, taking into consideration the content of the information and all other relevant circumstances (which may include the timing of the request).
55. The Authority relied upon section 30(c) (prejudice substantially, the effective conduct of public affairs) to withhold information in the documents.
The Authority’s submissions on section 30(c)
56. The Authority submitted that it was essential for it to have a productive relationship with companies like GFG, which run businesses of national and local importance to Scotland. As the Lochaber smelter is a significant employer in the local area, the Authority had a significant interest in the business through the Guarantee.
57. The Authority provided three key reasons for withholding the information under the exemption in section 30(c) of FOISA, as follows:
Point (a) – Disclosure would weaken the Authority’s ability to negotiate guarantee terms
58. The Authority submitted that it was likely that external lenders will be involved in situations where it is providing guarantees to support businesses. It would be in these lenders’ interests to negotiate the most generous guarantee terms possible, thereby passing risk to the Authority (which would be to the detriment of the Authority’s interests were such a guarantee more likely to be called up). Disclosure would enable future lenders to form views about the Authority’s likely appetite for risk and on how it takes decisions on these matters, and would allow them to use this as part of their negotiation strategy. The Authority believed the process of benchmarking one guarantee against another would ultimately be detrimental to its interests.
Point (b) – Disclosure would make distressed businesses less likely to engage with Authority support
59. The Authority submitted that businesses are extremely hesitant to consider financial intervention sponsored by it, or its Agencies, due to the risk of this becoming public knowledge, as this would alert customers and suppliers to the fact that the business was utilising last resort funding to continue to trade. This, in turn, would adversely affect the business as its customers and suppliers would be less willing to deal with it due to fear of wasted costs (e.g. where the business was unable to pay for materials ordered), leading to further difficulties in trading.
60. In the Authority’s view, disclosure would exacerbate the issue by underscoring not only that fact, but also the underlying basis on which decisions are made about sensitive business operations and situations, and this risk was not one that arose where a business secured support from a third party which was not a Scottish public authority. The Authority also believed this would heighten concerns about seeking support from the Authority, making such support less effective and thereby prejudicing its own commercial interests.
61. The Authority argued that it must be able to assure businesses that sensitive information about their financial position and future plans will not be released as a result of their involvement with the Authority. In the Authority’s view, maintenance of trust was important to allow it to engage with businesses in the best interests of Scotland, with the ultimate aim of preserving employment and growing the economy. It believed that disclosure of the information would jeopardise its ability to work in partnership with commercial actors such as GFG in future.
Point (c) – Disclosure would remove the private space for consideration that is required by the Authority to make decisions in relation to a significant contract with implications for jobs and the economy
62. The Authority submitted that the Guarantee was a live agreement, and it was required to take decisions in relation to the management of the Guarantee. It argued that release of information relating to the Guarantee, including the terms of the Guarantee, would inhibit substantially its ability to make such decisions in the public interest, by removing the private space required for it to do so.
63. The Authority considered that disclosure would also substantially prejudice its relationship with GFG. In its view, disclosing the content of a live agreement to which GFG is party could negatively impact on GFG’s financial operations in a number of stated ways. The Authority believed that GFG would likely consider that it had revealed sensitive details which were shared on a confidential basis in respect of the agreement, which would be detrimental to GFG and its ongoing relationship with the Authority.
The Applicant’s submissions on section 30(c)
64. The Applicant disagreed that the exemption in section 30(c) was engaged. In their view, disclosure of the withheld information would not result in the significant probability of substantial prejudice.
65. In respect of point (a) above, the Applicant submitted that the Authority had not substantiated the link between the specific information, disclosure and harm. They argued that the Lochaber Smelter Guarantee and Reimbursement Agreement (GRA) was a novel, highly unusual agreement with a financing firm (Greensill Capital (UK) Ltd) which was not authorised and regulated by the Financial Conduct Authority, and which had subsequently collapsed into administration. In their view, the unique nature of this agreement would not compromise negotiations in future guarantees.
66. In respect of point (b) above, the Applicant did not believe there was any requirement for the Authority to obtain the consent of the participating companies prior to disclosing information. In their view, the participating companies will have engaged into the GRA knowing that the Authority was a public authority for the purposes of FOISA, and so information could be disclosed solely at the discretion of the Authority. They argued that the agreement should contain a clause to that effect.
The Commissioner’s view on section 30(c)
67. Information can only be exempt under section 30(c) of FOISA if its disclosure would prejudice substantially, or be likely to prejudice substantially, the effective conduct of public affairs.
68. The Commissioner must consider the withheld information with regard to the circumstances at the time of the Authority’s review outcome. Given the sensitivity of the information and the circumstances surrounding it, the Commissioner is limited in the reasoning he can set out in this Decision Notice.
69. The Commissioner notes that the main focus of the withheld information is financial arrangements and discussions of the commercial companies’ information within the documents which were, at the date of the Authority’s review response, relatively recent.
70. For example, at the date of the Authority’s review response, the financial viability of the companies involved (Greensill and CFG) had changed considerably, but the Authority would still have to pay for 80% of the power that SmelterCo is contracted to purchase from HydroCo in the event that SmelterCo is unable to do so.
71. Having considered the nature and content of the withheld information, together with the submissions of the Authority and the Applicant, the Commissioner finds that disclosure of the withheld information would, or would be likely to, have a detrimental impact on the Authority, CFG and the other commercial companies’ ability to continue in a competitive environment, which, in turn, would, or would be likely to, impede the Authority’s ability to engage with businesses in the best interests of Scotland.
72. The Commissioner cannot expand on his reasoning here, as to do so would reveal the information being withheld.
73. In the circumstances, the Commissioner is satisfied that the Authority was entitled to apply the exemption in section 30(c) of FOISA to the withheld information.
Public interest test
74. The exemption in section 30(c) is subject to the public interest test in section 2(1)(b) of FOISA. The Commissioner must therefore go on to consider whether, in all the circumstances of the case, the public interest in disclosing the information is outweighed by that in maintaining the exemption.
The Authority's submissions on the public interest – section 30(c)
75. The Authority recognised the public interest in disclosure, as part of an open, transparent and accountable government and to inform public debate. It also recognised the public interest in the aluminium smelter complex, and in how the Authority works with companies such as GFG when public funds are involved.
76. However, given the importance of the smelter to Scotland, the Authority believed this was outweighed by the public interest in protecting GFG’s trust in its relationship with the Authority.
77. The Authority argued that it was of vital importance to Scotland and its people that it was able to intervene to protect jobs and the wider economy. When this involved a guarantee, such as this one, the Authority believed the public interest lay in protecting certain sensitive information to allow future interventions.
78. The Authority submitted that, ultimately, the aim of this intervention was to protect jobs, and there was no public interest in disclosing information that would jeopardise such future action.
79. The Authority believed the public interest lay in protecting the interests of those employed within the Lochaber smelter business (circa 200 people), given its importance not only to those employees, but also to the wider economy of the local area.
The Applicant's submissions on the public interest – section 30(c)
80. The Applicant submitted a number of arguments in support of their position that the public interest favoured disclosure of the information. In their view, there was a public interest:
• in ensuring the Guarantee agreement and the Authority’s actions complied with all laws and regulations;
• in ensuring the Scottish Parliament’s Finance and Constitution Committee was provided with complete and accurate information by the Authority, and that it provided effective independent scrutiny prior to approving the £586m contingent liability;
• in subjecting the financial guarantee to broad public scrutiny to increase the quality of the scrutiny over that achievable by a small number of politicians (lay people);
• in disclosure, because of suspected fraud and money-laundering between two of the key parties (GFG and Greensill Capital (UK) Limited), because the Guarantee was not based on sound data, and because one of the key parties to the agreement (Greensill Capital (UK) Limited) was now in administration;
• in ensuring the agreement was robust and at arm’s length, with no mutual reward between the Authority and other parties to the agreement, and that it provided value for money at all stages (from approval to delivery);
• in disclosure, in order to evaluate relative spending priorities and to be able to independently monitor and measure approved project outcomes;
• in disclosure, because of the financial size (£586m), the unusual term (25 years), the nature and the complexity of the agreement;
• in understanding the Authority’s exposure to the GRA; and
• in understanding the security and guarantees the Authority has obtained from GFG member companies for entering into the agreement and, specifically, whether they were adequate.
81. Separately, the Applicant made the following arguments (see paragraph 26) which were also relevant to the public interest test:
• the Guarantee did not directly support existing jobs;
• the Guarantee provided protection to Greensill and not GFG;
• the funding enabled by the Guarantee was not “last resort funding” in relation to the Lochaber complex;
• the funding had not prevented the fragmentation of the Lochaber smelter complex;
• there was no independent evidence to support the Authority’s assertion that the fee was at a commercial level; and
• “secrecy” over high-value government contracts was a “red flag of potential fraud” and GFG was under investigation by the Serious Fraud Office.
The Commissioner’s view on the public interest – section 30(c)
82. The Commissioner has taken account of all of the relevant submissions from both parties, together with the withheld information in this case. He is required to balance the public interest in disclosure of the information requested against the public interest in maintaining the exemption. The public interest, in the context of FOISA, should be considered as “something which is of serious concern and benefit to the public”.
83. As rehearsed above, the Commissioner has already accepted that disclosure of the withheld information would, or would be likely to, cause substantial prejudice to the effective conduct of public affairs.
84. Given the significant size of the Lochaber Smelter Guarantee and those potentially affected by the circumstances surrounding it, the Commissioner accepts that there is clear and substantial public interest in understanding the finer details of the Guarantee and discussions that the Authority had with Greensill and other companies.
85. However, the Commissioner recognises that this must be carefully balanced against any impact that disclosure of the withheld information would have had – at the time when the Authority issued its review outcome – with regard to the Lochaber smelter, the Guarantee itself (underwritten by the Authority) and what the likely circumstances might be were the Guarantee to be called in.
86. The Commissioner acknowledges that, were circumstances to arise requiring the Guarantee to be called in, this would clearly impact the parties involved (including the Authority), the economy of the local area (and the wider Scottish economy) and the jobs of those individuals employed at the smelter and associated businesses, both directly and indirectly.
87. The Commissioner recognises that such a situation could lead to a number of unwanted circumstances presenting themselves, for example job losses, the requirement for a new agreement to be drawn up or entered into by the Authority, and a reduction in crucial commercial information being provided by businesses to the Authority which would inhibit the Authority’s ability to take fully informed decisions and secure best value for public money. Such circumstances would clearly impact on the Authority’s position with regard to its ability to effectively conduct its public affairs, and that would not be in the public interest.
88. On balance, therefore, the Commissioner is of the view that the public interest in withholding the remaining information outweighs the public interest in disclosing it.
89. The Commissioner therefore finds that the Authority was entitled to withhold the information he has found to be exempt under section 30(c) of FOISA.
Decision
The Commissioner finds that the Authority partially complied with Part 1 of the Freedom of Information (Scotland) Act 2002 (FOISA) in responding to the information request made by the Applicant.
The Commissioner finds that, by relying upon section 30(c) of FOISA to withhold information within the documents, the Authority complied with Part 1.
However, by disclosing further information to the Applicant subsequent to its review response, the Authority failed to comply with section 1(1) of FOISA.
Given that all non-exempt information has been disclosed, the Commissioner does not require the Authority to take any action in respect of this failure in response to the Applicant’s application.
Appeal
Should either the Applicant or the Authority wish to appeal against this decision, they have the right to appeal to the Court of Session on a point of law only. Any such appeal must be made within 42 days after the date of intimation of this decision.
David Hamilton
Scottish Information Commissioner
4 June 2024
Appendix 1: Relevant statutory provisions
Freedom of Information (Scotland) Act 2002
1 General entitlement
(1) A person who requests information from a Scottish public authority which holds it is entitled to be given it by the authority.
(2) The person who makes such a request is in this Part and in Parts 2 and 7 referred to as the “applicant.”
…
(4) The information to be given by the authority is that held by it at the time the request is received, except that, subject to subsection (5), any amendment or deletion which would have been made, regardless of the receipt of the request, between that time and the time it gives the information may be made before the information is given.
…
(6) This section is subject to sections 2, 9, 12 and 14.
2 Effect of exemptions
(1) To information which is exempt information by virtue of any provision of Part 2, section 1 applies only to the extent that –
(a) the provision does not confer absolute exemption; and
(b) in all the circumstances of the case, the public interest in disclosing the information is not outweighed by that in maintaining the exemption.
….
30 Prejudice to effective conduct of public affairs
Information is exempt information if its disclosure under this Act-
…
(c) would otherwise prejudice substantially, or be likely to prejudice substantially, the effective conduct of public affairs.
47 Application for decision by Commissioner
(1) A person who is dissatisfied with -
(a) a notice under section 21(5) or (9); or
(b) the failure of a Scottish public authority to which a requirement for review was made to give such a notice.
may make application to the Commissioner for a decision whether, in any respect specified in that application, the request for information to which the requirement relates has been dealt with in accordance with Part 1 of this Act.
(2) An application under subsection (1) must -
(a) be in writing or in another form which, by reason of its having some permanency, is capable of being used for subsequent reference (as, for example, a recording made on audio or video tape);
(b) state the name of the applicant and an address for correspondence; and
(c) specify –
(i) the request for information to which the requirement for review relates;
(ii) the matter which was specified under sub-paragraph (ii) of section 20(3)(c); and
(iii) the matter which gives rise to the dissatisfaction mentioned in subsection (1).